Manufacturing Types and Strategies
The type of manufacturing determines which ERP module you configure, which data objects exist, and which metrics matter. Getting this classification right on day one saves an implementation.
Production types
Discrete manufacturing
Countable, distinct units. Cars, phones, furniture, machinery, garments.
- BOM — a parts list with quantities
- Routing — a sequence of operations at work centres
- Production order — makes N units of one product
- Assembly-oriented; you can disassemble it back into parts
- Metric focus: units per hour, first-pass yield, OEE
Process manufacturing
Continuous or batch flows of materials that can’t be un-mixed. Chemicals, food, pharma, paint, cement, refining.
- Recipe / master recipe / formula instead of a BOM
- Resources instead of work centres
- Process order with phases and operations
- Co-products and by-products — one process yields several outputs
- Yield and potency — output isn’t a fixed multiple of input
- Scaling — the recipe scales to batch size, sometimes non-linearly
- Metric focus: yield %, throughput, batch cycle time, first-time-right
Repetitive manufacturing
High-volume, same product, continuous flow. Consumer goods, electronics, automotive components.
- No individual production orders — you’d drown in them
- Production version + rate routing (units per hour, not time per unit)
- Backflushing — components consumed automatically based on output reported
- Reporting points — confirm at a few checkpoints, not every operation
- Metric focus: takt time, line rate, changeover time
Project manufacturing (ETO)
One-of-a-kind, engineered to order. Ships, plants, buildings, custom machinery.
- WBS / project structure drives everything
- BOM and routing are created during the project, not before
- Long lead times, progress billing, percentage-of-completion revenue
- Engineering change is constant
- Metric focus: cost to complete, schedule variance, earned value
Lean / Kanban
Pull-based replenishment, minimal formal orders.
- Kanban containers signal replenishment when emptied
- No MRP for kanban-controlled items
- Heijunka (levelling), JIT, one-piece flow
- Metric focus: WIP, lead time, inventory turns
Planning strategies (the decoupling point)
Decoupling point
↓
MTS [forecast ──────────────────────────────────] [order] Ship
Stock finished goods
ATO [forecast ──────────────────] [order ────────────────] Ship
Stock components, assemble on order
MTO [forecast ──────] [order ────────────────────────────] Ship
Stock raw materials, make on order
ETO [order ────────────────────────────] Ship
Design and make on order
| Strategy | Lead time to customer | Inventory risk | Variety possible |
|---|---|---|---|
| MTS | Immediate | High (finished goods) | Low |
| ATO | Days | Medium (components) | High |
| MTO | Weeks | Low (raw materials) | Very high |
| ETO | Months | None | Unlimited |
ATO is the sweet spot for configurable products — Dell’s original model. Stock the modules, assemble the combination. It needs a variant configurator and a modular BOM.
Manufacturing execution objects
| Object | Discrete | Process | Repetitive | Project |
|---|---|---|---|---|
| Structure | BOM | Recipe/Formula | BOM | Project BOM |
| Process | Routing | Master recipe | Rate routing | Network activities |
| Resource | Work centre | Resource | Production line | Work centre / crew |
| Order | Production order | Process order | Production version + backflush | Network / WBS |
| Confirmation | Per operation | Per phase | Per reporting point | Per activity |
| Costing | Order-based | Order-based | Period-based | Project-based |
Key manufacturing concepts
Lead time components
Queue time waiting before the operation starts ← usually the biggest
+ Setup time changeover, tooling
+ Run time actual processing (qty × time per unit)
+ Wait time after the operation, before moving
+ Move time transport to the next work centre
= Throughput time
Queue time typically dominates — often 80–95% of total throughput time in a job shop. This is why reducing batch sizes shortens lead times far more than making machines faster.
Lot sizing on the shop floor
- Order quantity — how much you make at once
- Transfer/overlap quantity — you don’t have to finish all 1,000 at operation 10 before starting operation 20. Splitting into transfer batches overlaps operations and can cut throughput time by 50%+
- Splitting — running one order on parallel machines
Yield and scrap
Input 1,000 kg → Output 940 kg
Yield 94%, scrap 6%
Planned scrap: built into the BOM/routing, expected, in the standard cost
Unplanned scrap: a variance, investigated
Distinguishing planned from unplanned is what makes scrap analysable. If all scrap is unplanned, every order shows a variance and nobody looks at any of them.
Co-products and by-products
Crude oil refining → Petrol (co-product) ← cost allocated
Diesel (co-product) ← cost allocated
Bitumen (by-product) ← credited at NRV, not allocated
Waste ← disposal cost
Cost allocation between co-products uses relative sales value, physical units, or a fixed apportionment. It’s a genuine accounting decision, not a technical one, and it moves reported product profitability significantly.
OEE — Overall Equipment Effectiveness
The universal manufacturing metric:
OEE = Availability × Performance × Quality
Availability = run time / planned production time (breakdowns, changeovers)
Performance = (ideal cycle × units) / run time (slow running, minor stops)
Quality = good units / total units (defects, rework)
Example: 0.90 × 0.85 × 0.98 = 75%
World class is ~85%. Typical is 40–60%. The value of OEE is the breakdown: 75% could be an availability problem or a quality problem, and the fixes are completely different.
The six big losses: breakdowns, setup/adjustment, small stops, reduced speed, startup rejects, production rejects.
Choosing the right module
Ask these questions:
- Can you count the units, or do you measure them? Countable → discrete. Measured → process.
- Does one process produce multiple valuable outputs? → process manufacturing with co-products.
- Do you make the same thing continuously? → repetitive with backflushing.
- Is each order unique and engineered? → project manufacturing.
- Do you need to trace a batch for recall? → batch management, mandatory in food/pharma/chemicals.
- Does the recipe scale non-linearly? → process, with a scaling formula.
- Are you assembling from stocked modules? → ATO with a variant configurator.
Most real companies are mixed: a food company does process manufacturing for the product and discrete for the packaging line. Configure both; don’t force one model on everything.